This plant was moved from the US to Chile. During the process, equipment update and overhaul were carried out. the installation of a Pulverized Carbon Injection system to the existing boiler in order to utilize the available fuel was one basic improvement
Nominal Power: 1 x 150 MW.
Boiler: Foster Wheeler.
Fuel: Pulverized Coal.
SteamTurbine Generator: GE.
Operator: CELTA S.A.(ENDESA S.A.)
Status: Operational
JV Mecánica de la Peña + Foster Wheeler + GE.
2011
Patache, Chile.
Engineering, Consultancy and Design:
Engineering Package.
Supervision of Construction & Commissioning.
EPC/Turnkey project:
EPC for Pulverized Coal Injection Package.